Question: I need to use the critical path method and draw a network diagram to solve this. NOT early start and late start ( 1 )
I need to use the critical path method and draw a network diagram to solve this. NOT early start and late start
The following is a list of tasks that have to be completed as soon as possible.
a What are the critical activities for this project?
b Is the critical path unique? Yes or No
c How soon can the project be completed?
d What is the total float of activity F
e If activity A is made shorter by hour, would the project take less time to complete? YES or NO
Explain briefly.
f If activity B is made shorter by hour, would the project take less time to complete? YES or NO Explain
briefly.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
