Question: . ( i ) One person using a hammer will take 5 days to nail new shingles on the roof of a 3 0 0
i One person using a hammer will take days to nail new shingles on the roof of a m house.
ii Two persons using a hammer but working together one holds a shingle, the other swings the hammer will take days to do the same job.
iii One person using a nail gun will take day to do the same job.
a Calculate the labour productivity in m per worker per day for each of the above cases.
a Labour productivity is defined as real output per labor hour and growth in labor productivity is measured as change in this ratio over time. It is also known as workforce productivity which is defined as real economic output per labor hour. Now, we will calculate labour productivity in this step.
i One person using a hammer will take days to nail new shingles on the roof of a m house. Labour Productivity mm
ii Two persons using a hammer but working together one holds a shingle, the other swings the hammer will take days to do the same job.
Labour Productivity mm
iii One person using a nail gun will take day to do the same job.
Labour Productivity mm
b Calculate the change in productivity due to method change, ie from i to ii
c Calculate the change in productivity due to using technology, ie from i to iii
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock