Question: ( 3 marks: 1 . 5 , 1 , 0 . 5 ) ( i ) One person using a hammer will take 5 days

(3 marks: 1.5,1,0.5)
(i) One person using a hammer will take 5 days to nail new shingles on the roof of a 300m2 house.
(ii) Two persons using a hammer but working together (one holds a shingle, the other swings the hammer) will take 2 days to do the same job.
(iii) One person using a nail gun will take 1 day to do the same job.
a. Calculate the labour productivity (in m2 per worker per day) for each of the above cases.
b. Calculate the % change in productivity due to method change, i.e., from (i) to (ii).
c. Calculate the % change in productivity due to using technology, i.e., from (i) to (iii).
 (3 marks: 1.5,1,0.5) (i) One person using a hammer will take

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!