Question: . ( i ) One person using a hammer will take 5 days to nail new shingles on the roof of a 3 0 0
i One person using a hammer will take days to nail new shingles on the roof of a m house. ii Two persons using a hammer but working together one holds a shingle, the other swings the hammer will take days to do the same job. iii One person using a nail gun will take day to do the same job. a Calculate the labour productivity in m per worker per day for each of the above cases. b Calculate the change in productivity due to method change, ie from i to ii c Calculate the change in productivity due to using technology, ie from i to iii