Question: i put 668 for Q17 but it was wrong :( thank you for helping me The following table gives the precedence requirements, normal and crash



The following table gives the precedence requirements, normal and crash activity time, and normal and crash costs for a project. Crash time is the shortest possible activity time and crash cost is the cost associated with the crash time. (Activity C can't be crashed) Activity Predecessors Normal Normal Crash time Crash costs Crash costs /day time (days) costs (S) (days) (S) (S) A None 20 320 15 570 ? None 16 480 13 600 ? C None 12. 290 NA ? D AB 20 250 10 330 ? 18 340 15 700 F BE 14 600 12 900 2 B NA E Question 13 2 pts What is the critical path of the project? Start-A-D-End Start-B-D-End O Start-B-F-End Start-C-E-F-End Question 14 2 pts What is the duration of the project (using normal time)? Report an integer. 100 Question 16 5 pts We want to shorten the duration of the whole project to 39 days while minimizing the total costs. To minimize the cost, you would crash Afor Select] days B for [Select] days D for (Select) days . E for (Select) days Ffor Select days Question 17 2 pts What will be the new cost of the project when the duration is shortened to 39 days? Report an integer without the comma
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts