Question: I will thumb up The information about a project with 10 activities is shown below. Activity A; 12 days, IP = none Activity B; 14

I will thumb up I will thumb up The information about a project
The information about a project with 10 activities is shown below. Activity A; 12 days, IP = none Activity B; 14 days; IP = none Activity C; 34 days; IP = A Activity D; 31 days; IP = A, B Activity E; 32 days; IP = B Activity F; 39 days; IP = C, D Activity G: 28 days; IP = C, D Activity H; 30 days; IP = E Activity K: 22 days; IP = F Activity M; 7 days: IP = G, H The earliest finish time of activity M is at the end of day