Question: The information about a project with 10 activities is shown below. Activity A;15 days; IP= none Activity B;19 days; IP= none Activity C;28 days; IP=A

The information about a project with 10
The information about a project with 10 activities is shown below. Activity A;15 days; IP= none Activity B;19 days; IP= none Activity C;28 days; IP=A Activity D;32 days; IP=A Activity E;30 days; IP=A,B Activity F;29 days; IP=C Activity G;36 days; IP=D,E Activity H;16 days; IP=E Activity K;26 days; IP=F Activity M; 20 days; P=F,G,H Perform the forward and backward passes of CPM. The project completion time is days