Question: The information about a project with 10 activities is shown below. Activity A; 20 days; IP = none Activity B; 25 days; IP = none
The information about a project with 10 activities is shown below.
Activity A; 20 days; IP = none Activity B; 25 days; IP = none Activity C; 38 days; IP = A Activity D; 43 days; IP = A, B Activity E; 32 days; IP = B Activity F; 31 days; IP = C, D Activity G; 38 days; IP = C, D Activity H; 26 days; IP = E Activity K; 11 days; IP = F Activity M; 11 days; IP = G, H
The latest start time of activity D is at the end of day __________.