Question: i would really appreciated if answer this question quickly thank you all for help. Given the following project: Crash Cost Activity Predecessor Normal Time (dayl

i would really appreciated if answer this question quickly thank you all for help.

i would really appreciated if answer this

Given the following project: Crash Cost Activity Predecessor Normal Time (dayl Normal Cost (S) Crash Time (day) (5) 800 10 1200 1100 1000 2000 900 1300 2400 1700 1600 3000 - A,B 7 C 10 CD 5 (a) Draw the network and find the critical path duration of the project, total cost of project using normal times. (b) Calculate the maximum time reduction and crash cost-per-day (all activities may be partially crashed) for each activity. Then fill the table below. (Note: Activity "F" cannot be crashed) Activity Maximum Time Reduction (day) Cost to Crash per Period ($/day) (c) Find the optimal way of getting a 20 day delivery time. What is the project cost? (d) Find the optimal way of getting a 18-day delivery time. What is the project cost

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!