Question: i would really appreciated if answer this question quickly thank you all Activities of a project are provided below: Activity a Immediate predecessor Time (days)

i would really appreciated if answer this question quickly thank you all

i would really appreciated if answer this

i would really appreciated if answer this

i would really appreciated if answer this

Activities of a project are provided below: Activity a Immediate predecessor Time (days) b | 8 10 4 5 11 1 0 4 14 BD 21 GF | E,H D G Activity Exp. Standard Duration Deviation Duration Variance ESEF LS > IIIIIIIIII - - - - e) (2 pts) Identify those activities comprising the critical path. f) (2 pts) What is the project's estimated (expected) duration? g) (2 pts) Find the probability that the project will be completed in 25 days or less. h) (2 pts) Find the probability that the project will be completed in 28 days or less. i) (2 pts) Provide a deadline of the project on which the project can be completed with 95% probability, j) (2 pts) Explain the effect on project duration; i. if only expected duration (Te) of activity B changes to 7 days? ii. if only expected duration (Te) of activity D changes to 7 days? iii. if only expected duration (Te) of activity G changes to 7 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!