ID Predecessor A B D E F G H None None A A,B A,B

ID Predecessor A B D E F G H None None A A,B A,B C D,F E,G Optimistic (a) 6 5 11 10 20 6 2 6 Duration (Time/Days) Most Likely (m) Pessimistic (b) 10 26 6 13 14 17 12 20 24 34 11 22 3 10 9 12 (0) Construct an Activity on Arrow (AOA) Network diagram and determine ES, EF, LS, LF and TFS for the Activities. State the expected completion time for the research project and the critical activities Find the completion duration of this project to be scheduled to obtain a probability of 99% and find the probability if the project is scheduled for 65 days