Question: ID Predecessors m (weeks) Variance Late Start 0 a (weeks) 2 b (weeks) 6 A 4 (b-a)2/36 B A 4 4 6 8 Activity Define

ID Predecessors m (weeks) Variance Late Start 0 a

ID Predecessors m (weeks) Variance Late Start 0 a (weeks) 2 b (weeks) 6 A 4 (b-a)2/36 B A 4 4 6 8 Activity Define Requirements Design Application Draft User Manual Prepare A 10 4 5 6 D A 6 8 10 Code E Test Code B,C 10 2 3 4 F Correct Code E,D 12 3 4 5 What is the probability that the project will be finished in less than 17 weeks