Question: ID Task Predecessor Duration ES ID EF A Form project team None 1 SL Description B Interview users A 5 LS DUR LF C Survey

ID Task Predecessor Duration ES ID EF
A Form project team None 1 SL Description
B Interview users A 5 LS DUR LF
C Survey users A 3
D Identify new features B, C 2
E Acquire materials D 4
F Develop Marketing campaign D 2
G Produce Prototype E 3
H Design Graphics F 3
I Conduct marketing F 5
J Perform sales calls G, H, I 3
Help build network Diagram and Gnatt
Chart