Question: ... Put your name in cell B8 There are two backhoes available, nicknamed Ruby and Wanda 1 Create a network diagram and calculate ES, LF,
...
Put your name in cell B8 There are two backhoes available, nicknamed Ruby and Wanda 1 Create a network diagram and calculate ES, LF, SL for each activity (8 points) 2 Create a Gantt chart showing non-constrained time-phased resources scheduled in each time period. Calculate ES, LF, SL for each activity (7 points) 3 Copy the Gantt chart from #2 and develop a resource constrained schedule in the Gantt chart. No splitting. Recalculate ES, LF, SL for each activity. (20 points) 4 Recreate the network diagram from the constrained resource schedule (10 points) 5 Create a responsibility matrix (pg 122) for this project (5 points) ES ID EF SL Resource Network Diagram LS DUR LF A ID Res Predessor Dur ES LF SL A 1 None 1 B 1 None 2 1 None 3 D 1 A, B 2 E 2 B, C 4 F 2 DE 2 Gantt ID Res Predessor Dur ES LF SLO 1 2 3 4 5 6 7 8 9 10 11 A 1 None 1 Non-constrained B 1 None 2 Before 1 None 3 D 1 A,B 2 E 2 B, C 4 F 2 DE 2 Resource scheduled 0 0 0 0 0 0 0 0 0 0 Resource available 2 2 2 2 2 2 2 2 2 2 2 2 2 Gantt ID Res Predessor Dur ESLF SL o 1 2 3 4 5 6 7 8 9 10 11 A 1 None 1 Constrained B 1 None 2 After 1 None 3 D 1 AB 2 Priorities E 2 B, C 4 1: Minimum slack F 2 DE 2 2: Smallest duration 2 Resource scheduled 0 0 0 0 0 0 0 0 0 0 0 3: Lowest ID letter Resource available 2 2 2 2 2 2 2 2 2 2 2 2 ES ID EF SL Resource Resource constrained network diagram LS DUR LF ID Res Predessor Dur ES LF SL 1 None 1 B 1 None 2 1 None 3 D 1 AB 2 E 2 B, C 4 F F 2 DE 2 Responsibility Matrix Backhoes Available 0 0 Wanda Task Ruby B D E F Put your name in cell B8 There are two backhoes available, nicknamed Ruby and Wanda 1 Create a network diagram and calculate ES, LF, SL for each activity (8 points) 2 Create a Gantt chart showing non-constrained time-phased resources scheduled in each time period. Calculate ES, LF, SL for each activity (7 points) 3 Copy the Gantt chart from #2 and develop a resource constrained schedule in the Gantt chart. No splitting. Recalculate ES, LF, SL for each activity. (20 points) 4 Recreate the network diagram from the constrained resource schedule (10 points) 5 Create a responsibility matrix (pg 122) for this project (5 points) ES ID EF SL Resource Network Diagram LS DUR LF A ID Res Predessor Dur ES LF SL A 1 None 1 B 1 None 2 1 None 3 D 1 A, B 2 E 2 B, C 4 F 2 DE 2 Gantt ID Res Predessor Dur ES LF SLO 1 2 3 4 5 6 7 8 9 10 11 A 1 None 1 Non-constrained B 1 None 2 Before 1 None 3 D 1 A,B 2 E 2 B, C 4 F 2 DE 2 Resource scheduled 0 0 0 0 0 0 0 0 0 0 Resource available 2 2 2 2 2 2 2 2 2 2 2 2 2 Gantt ID Res Predessor Dur ESLF SL o 1 2 3 4 5 6 7 8 9 10 11 A 1 None 1 Constrained B 1 None 2 After 1 None 3 D 1 AB 2 Priorities E 2 B, C 4 1: Minimum slack F 2 DE 2 2: Smallest duration 2 Resource scheduled 0 0 0 0 0 0 0 0 0 0 0 3: Lowest ID letter Resource available 2 2 2 2 2 2 2 2 2 2 2 2 ES ID EF SL Resource Resource constrained network diagram LS DUR LF ID Res Predessor Dur ES LF SL 1 None 1 B 1 None 2 1 None 3 D 1 AB 2 E 2 B, C 4 F F 2 DE 2 Responsibility Matrix Backhoes Available 0 0 Wanda Task Ruby B D E F