Question: Put your name in cell B 8 There are two backhoes available, nicknamed Ruby and Wanda 1 Create a network diagram and calculate ES ,

Put your name in cell B8
There are two backhoes available, nicknamed Ruby and Wanda
1 Create a network diagram and calculate ES, LF, SL for each activity (8 points)
2 Create a Gantt chart showing non-constrained time-phased resources scheduled in each time period. Calculate ES, LF, SL for each activity (7 points)
3 Copy the Gantt chart from #2 and develop a resource constrained schedule in the Gantt chart. No splitting. Recalculate ES, LF, SL for each activity. (20 points)
4 Recreate the network diagram from the constrained resource schedule (10 points)
5 Create a responsibility matrix (pg 122) for this project (5 points)
Venkata Nikitha Gedala
ES ID EF
SL Resource Network Diagram
LS DUR LF
A
ID Res Predessor Dur ES LF SL
A 1 None 1
B 1 None 2
C 1 None 3
D 1 A, B 2
E 2 B, C 4
F 2 D,E 2
Gantt
ID Res Predessor Dur ES LF SL 01234567891011
A 1 None 1 Non-constrained
B 1 None 2 Before
C 1 None 3
D 1 A, B 2
E 2 B, C 4
F 2 D,E 2
Resource scheduled 000000000000
Resource available 222222222222
Gantt
ID Res Predessor Dur ES LF SL 01234567891011
A 1 None 1 Constrained
B 1 None 2 After
C 1 None 3
D 1 A, B 2 Priorities
E 2 B, C 41: Minimum slack
F 2 D,E 22: Smallest duration
Resource scheduled 0000000000003: Lowest ID letter
Resource available 222222222222
ES ID EF
SL Resource Resource constrained network diagram
LS DUR LF
A
ID Res Predessor Dur ES LF SL
A 1 None 1
B 1 None 2
C 1 None 3
D 1 A, B 2
E 2 B, C 4
F 2 D,E 2
Responsibility Matrix
Backhoes Available
Task Ruby Wanda
A
B
C
D
E
F

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!