Question: Identify five risks in this Gantt chart and define mitigation and contingency plans for each one. Answer using the project management tool provided below #

Identify five risks in this Gantt chart and

Identify five risks in this Gantt chart and define mitigation and contingency plans for each one. Answer using the project management tool provided below

#

Risk (What could go wrong?)

Reason (Why)

Responsible (who)

Likelihood1

Impact1

Ranking2

Mitigation (Action to be taken in advance)

Contingency (Action to be taken if the risk arises)

1

2

3

4

5

1 It ranges from 1 (low) to 5 (high)

2 It ranges from 1 (low) to 25 (high) from the multiplication of likelihood and Impact

Percent Complete Name Predecessors Mar 2020 Apr 2020 May 2020 Jun 2020 01 08 15 22 129 05 12 19 126 103 10 17 124 131 loz 114 Jul 2020 128105112 Aug 2020 126 102091 121 119 1 2 3 4 3 5 4 6 5 7 6 8 9 8 10 9 11 9 12 13 10 14 Duration Start Finish 114 days? 9/03/20 8:00 AM 13/08/20 5:00 PM 30 days 9/03/20 8:00 AM 17/04/20 5:00 PM 30 days 9/03/20 8:00 AM 17/04/20 5:00 PM 5 days 23/03/20 8:00 AM 27/03/20 5:00 PM 10 days 30/03/20 8:00 AM 10/04/20 5:00 PM 0 days 13/04/20 8:00 AM 13/04/20 8:00 AM 30 days? 13/04/20 8:00 AM 22/05/20 5:00 PM 1 day 13/04/20 8:00 AM 13/04/20 5:00 PM 9 days 14/04/20 8:00 AM 24/04/20 5:00 PM 5 days 27/04/20 8:00 AM 8/05/20 5:00 PM 5 days 27/04/20 8:00 AM 8/05/20 5:00 PM 1 day? 13/04/20 8:00 AM 13/04/20 5:00 PM O days 8/05/20 5:00 PM 8/05/20 5:00 PM 20 days 27/04/20 8:00 AM 22/05/20 5:00 PM 0 days 22/05/20 5:00 PM 22/05/20 5:00 PM 23 days 25/05/20 8:00 AM 24/06/20 5:00 PM 3 days 25/05/20 8:00 AM 27/05/20 5:00 PM 5 days 28/05/20 8:00 AM 3/06/20 5:00 PM 3 days 25/05/20 8:00 AM 27/05/20 5:00 PM 5 days 4/06/20 8:00 AM 10/06/20 5:00 PM 10 days 11/06/20 8:00 AM 24/06/20 5:00 PM 30 days 25/06/20 8:00 AM 5/08/20 5:00 PM 15 days 25/06/20 8:00 AM 15/07/20 5:00 PM 5 days 16/07/20 8:00 AM 22/07/20 5:00 PM 30 days 25/06/20 8:00 AM 5/08/20 5:00 PM 6 days 6/08/20 8:00 AM 13/08/20 5:00 PM 5 days 6/08/20 8:00 AM 12/08/20 5:00 PM 1 day 13/08/20 8:00 AM 13/08/20 5:00 PM 9 12% Project 44% Business Modelling 17% Perform marketing survey 100% Allocate project team leaders 100% Develop project proposal 100% Approve project proposal 2% Requirements, Analysis and Design 100% Kick-off meeting 0% Analyse requirements 0% Develop technical plan 0% Develop test plan 0% Perform unit test 0% Approve technical plan 0% Develop PMP 0% Approve PMP 0% Implementation 0% Develop hardware xyz 0% Develop unit test for hardware XYZ 0% Develop module software Z 0% Perform peer review 0% Integrate softwares A and hardware XYZ 0% Test 0% Systems testing 0% Acceptance testing 0% Rework 0% Deployment 0% Launch prototype 0% Release project team 15 14 16 17 15 18 17 19 15 20 17, 18:19 20 21 22 23 21 24 23 25 21 26 27 25 28 27

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!