Question: Identify the bottleneck by computing total workload at each workstation. The firm wants to satisfy as much of the product demand in a week as

Identify the bottleneck by computing total workload at
each workstation. The firm wants to satisfy as much of
the product demand in a week as it can. Each week
consists of 2400 minutes of available production time.
Multiplying the processing time at each station for a
given product with the number of units demanded per
week yields the capacity load. These loads are summed
across all products going through that workstation and
then compared with the existing capacity of 2400
minutes.