Question: Identify the duration is required to complete the upcoming project. Tasks Design Procurement Development Duration 6 days 7 days 10 days Priority/Relationship Start Will start
Identify the duration is required to complete the upcoming project.

Tasks Design Procurement Development Duration 6 days 7 days 10 days Priority/Relationship Start Will start after Task 1 is complete Will start after Task 1 is complete