Question: Identify the first step in the project scope management process from the following: Define Scope Create the WBS Collect Requirements Plan the scope management

Identify the first step in the project scope management process from the following:

  • Define Scope
  • Create the WBS
  • Collect Requirements
  • Plan the scope management