Question: If a delay in an activity will not delay completion of the whole project, the activity is on the critical path has slack is one


If a delay in an activity will not delay completion of the whole project, the activity is on the critical path has slack is one of the first tasks to be completed has a long expected completion time has a short expected completion time In making a backward pass through a network, activity L has an activity time of 6 and immediately precedes activities M,P, and T. The late start times for activities M, P, and T are 32,27 , and 26 , respectively. The late finish times for activities M,P, and T are 39,37 , and 33 , respectively. What is the late start time for activity L? 17 20 33 13 22 If a delay in an activity will not delay completion of the whole project, the activity is on the critical path has slack is one of the first tasks to be completed has a long expected completion time has a short expected completion time In making a backward pass through a network, activity L has an activity time of 6 and immediately precedes activities M,P, and T. The late start times for activities M, P, and T are 32,27 , and 26 , respectively. The late finish times for activities M,P, and T are 39,37 , and 33 , respectively. What is the late start time for activity L? 17 20 33 13 22
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts