Question: If a delay in an activity will not delay completion of the whole project, the activity _ _ _ _ _ _ _ _ _
If a delay in an activity will not delay completion of the whole project, the activity
Group of answer choices
has a long expected completion time
has slack
has a short expected completion time
is one of the first tasks to be completed
is on the critical path