Question: If a project closed successfully ( on time, budget, and within scope ) a lessons learned meeting isn't always necessary. Select one: a . True
If a project closed successfully on time, budget, and within scope a "lessons learned" meeting isn't always necessary.
Select one:
a True
b False
Clear my choice
is an uncertainty that may arise during the course of a project that will have a negative impact on the project's outcome.
Select one:
a Variance
b Conflict
c Risk
d An opportunity