Question: If a project's earned value is $ 1 8 , 0 0 0 and its planned value is $ 6 , 0 0 0 ,

If a project's earned value is $18,000 and its planned value is $6,000, what would its schedule performance index suggest?
a It will cost $24,000 to complete the schedule.
b It will cost $12,000 to complete the schedule.
c The project is behind schedule.
d The project is ahead of schedule.