Question: A project with Earned Value ( EV ) = $ 2 5 0 , Actual Cost ( A C ) = $ 2 0 0
A project with Earned Value EV$ Actual Cost $ and Planned Value $ What is the Schedule Performance Index SPI
a
b
c
d
A project with Earned Value EV$ Actual Cost $ and Planned Value PV$ What is the Cost Performance Index CPI
a
b
c
d
If and the project is:
a Ahead of schedule and under budget
b Ahead of schedule and over budget
c Behind schedule and over budget
d Behind schedule and under budget
If I and I then the trend for the project is:
a Running over budget but ahead of schedule
b Running over budget but behind schedule
c Running under budget but ahead of schedule
d Running under budget but behind schedule
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
