Question: If an activity cannot be delayed without affecting the entire project, it is a _ _ _ _ _ _ _ _ _ _ _

If an activity cannot be delayed without affecting the entire project, it is a _____________ activity.
Group of answer choices
completed
critical
conjugated
none of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!