Question: If an activity whose normal duration is 1 3 days can be shortened to 1 1 days for an added cost of $ 1 .

If an activity whose normal duration is 13 days can be shortened to 11 days for an added cost of $1.500, what is the crash cost per period?
$750
$500
$13,000
$15.000
$1,500
 If an activity whose normal duration is 13 days can be