Question: If an activity whose normal duration is 1 5 days can be shortened to 1 0 days for a total added cost of $ 2

If an activity whose normal duration is 15 days can be shortened to 10 days for a total added cost of $2,000, the crash cost per period is:
Group of answer choices
$2,000
$400
$20,000
$30,000
$10,000