Question: If an activity whose normal duration is 15 days can be shortened to 11 days for an added cost of $2,000, the crash cost per

If an activity whose normal duration is 15 days can be shortened to 11 days for an added cost of $2,000, the crash cost per period is

a.

$10000

b.

$500

c.

$30000

d.

$400

e.

$20000