Question: If an activity whose normal duration is 15 days can be shortened to 11 days for an added cost of $2,000, the crash cost per
If an activity whose normal duration is 15 days can be shortened to 11 days for an added cost of $2,000, the crash cost per period is
a.
$10000
b.
$500
c.
$30000
d.
$400
e.
$20000