Question: Question content area Part 1 If an activity whose normal duration is 1 5 days can be shortened to 1 1 days for an added

Question content area
Part 1
If an activity whose normal duration is 15 days can be shortened to 11 days for an added cost of $2,000, what is the crash cost per period?