Question: If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $10,000, the crash cost per

If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $10,000, the crash cost per period is

A.

$400

B.

$30,000

C.

$10,000

D.

$2,000

E.

$20,000