Question: If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $10,000, the crash cost per
If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $10,000, the crash cost per period is
A.
$400
B.
$30,000
C.
$10,000
D.
$2,000
E.
$20,000