Question: If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $2,000, what is the crash
If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $2,000, what is the crash time and crash cost per day?
Select one:
a. 10 days; $400
b. 10 days; $2,000
c. 5 days; $10,000
d. 10 days; $20,000
e. 5 days; $400