Question: If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $2,000, what is the crash

If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $2,000, what is the crash time and crash cost per day?

Select one:

a. 10 days; $400

b. 10 days; $2,000

c. 5 days; $10,000

d. 10 days; $20,000

e. 5 days; $400

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!