Question: If an activity whose normal duration is 50 days can be shortened to 34 days for an added cost of $6300, what is the crash
If an activity whose normal duration is 50 days can be shortened to 34 days for an added cost of $6300, what is the crash cost per period? (please round off to two decimal digits)