Question: If BCWP = $600, BCWS = $500, and ACWP = $900, what is schedule variance? Select one: a.-$300 b.-$100 c.$100 d.$300
If BCWP = $600, BCWS = $500, and ACWP = $900, what is schedule variance?
Select one:
a.-$300
b.-$100
c.$100
d.$300