Question: If BCWP = $600, BCWS = $500, and ACWP = $900, what is schedule variance? Select one: a.-$300 b.-$100 c.$100 d.$300

If BCWP = $600, BCWS = $500, and ACWP = $900, what is schedule variance?

Select one:

a.-$300

b.-$100

c.$100

d.$300