Question: Calculated the sample listed below then select the correct values for CV, Total ACWP, Total BCWS. Table A-WBS Activity Predecessor A B A Duration (days)


Calculated the sample listed below then select the correct values for CV, Total ACWP, Total BCWS. Table A-WBS Activity Predecessor A B A Duration (days) Cost/Day Total Cost 2 300 600 3 500 1500 3 400 1200 2 200 400 3 100 300 C D CT | B D B E Table B - Project Status Status report at end of day 7 Activity Actual % Complete Incurred Cost A 100 600 B 100 1400 C 600 D 200 E 0 0 Table C - Calculated Values CPI CV SPI SV Activity ACWP (AC) BCWP (EV) BCWS (PV) A 000D B Table C - Calculated Values Activity ACWP (AC) CPI BCWP (EV) CV BCWS (PV) SPI SV A B D E Total Select 3 correct answer(s) CV = 1.00 ing CV = .89 CV = .99 Total ACWP = 2800 Total ACWP = 2900 Total ACWP = 2850
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
