Question: If BCWS = 1 0 0 0 , BCWP = 1 2 0 0 and ACWP = 1 3 0 0 , the project is

If BCWS =1000, BCWP =1200 and ACWP =1300, the project is _________?
Question 7 options:
Ahead of schedule and under-budget
Ahead of schedule and over-budget
Behind schedule and over-budget
Behind schedule and under-budget