Question: If Critical Ratio ( CR ) = 1 , then, a the job is ahead of schedule b the job is exactly on schedule c

If Critical Ratio (CR)=1, then,
a the job is ahead of schedule
b the job is exactly on schedule
c the job is behind schedule
d the job cannot be done