Question: If cycle time is 3 and demand is 200 units in a ten-hour day... What is the line efficiency? (3) An electronics manufacturer makes remote

If cycle time is 3 and demand is 200 units in a

If cycle time is 3 and demand is 200 units in a ten-hour day...

What is the line efficiency?

(3) An electronics manufacturer makes remote control devices for interactive- cable-TV systems. The following assembly tasks must be performed on each device. Predecessor s) Time (min.) 0.50 Task Description A Place circuit into circuit frame Solder circuit connections to central B circuit control A 0.70 B 0.40 0.30 0.30 0.20 C Place circuit assembly in device frame Attach circuit assembly to device D frame E Place and attach display to frame F Place and attach keypad to frame Place and attach top body of device to G frame Place and attach battery holder to H frame Place and attach bottom body of device I to frame J Test device E, F 0.35 D 0.40 G H 0.60 0.30

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!