Question: If four workers (1 assigned to each task) are assigned to the following Four Task Assembly Line, which task will be the bottleneck? A four
If four workers (1 assigned to each task) are assigned to the following Four Task Assembly Line, which task will be the bottleneck?
A four task assembly line
A -> B -> C -> D
5mins 3mins 7mins 3mins
Question 8 options:
| Task A | |
| Task D | |
| Task B | |
| Task C |