Question: if integer constraints are added to a linear programming model, then the optimal objective value will improve. True /False? Suppose x 1 , x 2
if integer constraints are added to a linear programming model, then the optimal objective value will improve. True /False?
Suppose x1, x2, and x3 are binary variables that are equal to 1 if the corresponding project (1, 2, or 3) is selected and 0 if the corresponding project is not selected. Which constraint reflects the statement "at most two of these projects must be selected"?
| x1 + x2 = x3 | ||
| x1 + x2 + x3 = 2 | ||
| x1 + x2 + x3 2 | ||
| x1 + x2 + x3 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts