Question: If PV = $211, EV = $180 and AC = $212, the status is: (a) Under budget and behind schedule (b) Over budget and behind

If PV = $211, EV = $180 and AC = $212, the status is:

(a) Under budget and behind schedule

(b) Over budget and behind schedule

(c) Under budget and ahead of schedule

(d) Over budget and ahead of schedule

1b.

An activity in a network has the following characteristics: ES = 8, duration = 9, and slack is 3. LF = _____.

(a) 8

(b) 17

(c) 20

(d) 29