Question: If PV = $211, EV = $180 and AC = $212, the status is: (a) Under budget and behind schedule (b) Over budget and behind
If PV = $211, EV = $180 and AC = $212, the status is:
| (a) Under budget and behind schedule | ||||||||||||||
| (b) Over budget and behind schedule | ||||||||||||||
| (c) Under budget and ahead of schedule | ||||||||||||||
| (d) Over budget and ahead of schedule
1b. An activity in a network has the following characteristics: ES = 8, duration = 9, and slack is 3. LF = _____.
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
