Question: If t is the expected completion time for a given activity, then: If t is the expected completion time for a given activity, then: EF

If t is the expected completion time for a given activity, then:
If t is the expected completion time for a given activity, then:
EF = ES - t.
EF = LS - t.
LF = LS - t.
EF = ES + t.