Question: If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists? Start to Start Start

If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists?
Start to Start
Start to Finish
Finish to Start
Finish to Finish
Any of these could be correct