Question: If testing cannot be completed any earlier than four days after the prototype has been buin, what type of lag exists? Multiple Choice 0 0

If testing cannot be completed any earlier than four days after the prototype has been buin, what type of lag exists?
Multiple Choice
00:44:00
Start to Start
Finish to Finish
Finish to Start
Any of these could be correct