Question: MC Qu . 3 3 ( Static ) If testing cannot be completed any... If testing cannot be completed any earlier than four days after

MC Qu.33(Static) If testing cannot be completed any...
If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists?
Multiple Choice
Start to Start
Start to Finish
Finish to Finish
Finish to Start
Any of these could be correct