Question: If the BAC for a task is $70k, plan value is $40k, actual cost is $42k and percent complete is 60%, what is the SPI,
- If the BAC for a task is $70k, plan value is $40k, actual cost is $42k and percent complete is 60%, what is the SPI, CPI, and the TCPI for the project? How would you describe this project in terms of budget and schedule? (2 points)
Please show step by step
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
