Question: If the early start for activity A is equal to 23 months and the duration of activity A is equal to 5 months, what is
If the early start for activity A is equal to 23 months and the duration of activity A is equal to 5 months, what is the earliest finish for activity A?
| A. | 18 months | |
| B. | 23 months | |
| C. | 28 months | |
| D. | None of the above |
If the earliest finish for activity C is equal to 10 months and its duration 3 months, what is its earliest start?
| 10 months | ||
| 3 months | ||
| 7 months | ||
| None of the above |