Question: If the early start for activity A is equal to 23 months and the duration of activity A is equal to 5 months, what is

If the early start for activity A is equal to 23 months and the duration of activity A is equal to 5 months, what is the earliest finish for activity A?

A.

18 months

B.

23 months

C.

28 months

D.

None of the above

If the earliest finish for activity C is equal to 10 months and its duration 3 months, what is its earliest start?

10 months

3 months

7 months

None of the above