Question: If the engineer worked for 20 hours on a job, Z, the overhead rates were 125 per cent of direct labour cost and the direct
If the engineer worked for 20 hours on a job, Z, the overhead rates were 125 per cent of direct labour cost and the direct labour rate was $25 per hour, what is the total cost of the job?
A.
$500
B.
$625
C.
$1000
D.
$1125