Question: If the engineer worked for 20 hours on a job, Z, the overhead rates were 125 per cent of direct labour cost and the direct

If the engineer worked for 20 hours on a job, Z, the overhead rates were 125 per cent of direct labour cost and the direct labour rate was $25 per hour, what is the total cost of the job? show working

A. $500

B. $ 625

C. $1000

D. $1125