Question: If the engineer worked for 20 hours on a job, Z, and the rates were overhead 125 per cent on direct labour cost and the
If the engineer worked for 20 hours on a job, Z, and the rates were overhead 125 per cent on direct labour cost and the direct labour rate was $25 per hour, what is the total cost of the job?
Step by Step Solution
There are 3 Steps involved in it
To calculate the total cost of the job you can follo... View full answer