Question: If the net present value of a project is zero based on a discount rate of 1 6 % , then the internal rate of

If the net present value of a project is zero based on a discount rate of 16%, then the internal rate of return is:
Multiple Choice
equal to 16%.
cannot be determined from this data.
greater than 16%.
less than 16%.